Blog Archives

Substantial Completion Achieved at $13 Million CT DOT Milford Repair and Maintenance Facility

Rizzo Corporation achieved Substantial Completion on June 28th 2017 for our CTDOT Milford Repair and Maintenance Facility project. The project, constructed in two phases, consisted of over 43,000 square feet of new and renovated construction. Work included the construction and

Posted in CT DOT, Transportation

State of the Art Robotics at the NHRY’s Central Distribution Warehouse

Rizzo Corporation is currently the General Contractor on the New Haven Rail Yard’s Central Distribution Warehouse. Beginning in 2015 and wrapping up this year in 2017, the $21.9 Million project is a unique coordination effort between the MetroNorth and the

Tagged with: ,
Posted in CT DOT, DOT, Metro North, New Haven, Transportation, Warehouse